Levelized Cost of Energy (LCOE) Calculator

Levelized Cost of Energy (LCOE) Calculator

This tool estimates the Levelized Cost of Energy (LCOE) for a power generation project. LCOE represents the average cost of producing one unit of electricity (e.g., per kWh) over the project's lifetime, accounting for capital costs and the time value of money.

Enter the project's details below. Ensure consistent units for cost and capacity. The output is in dollars per kilowatt-hour ($/kWh).

Project Inputs

Total upfront cost ($)
Maximum output capacity (kW)
Average operational output relative to max (%)
Expected years of operation
Annual rate reflecting time value of money (%)

Understanding Levelized Cost of Energy (LCOE)

What is LCOE?

LCOE is a metric used in the economics of power generating sources, often for comparing alternative methods of electricity generation on a consistent basis. It represents the total cost of building and operating a power plant over its anticipated lifetime, divided by the total energy output over that lifetime. Crucially, it accounts for the time value of money using a discount rate.

The Simplified LCOE Calculation Used Here

This calculator uses a simplified LCOE model focusing on the most basic inputs. The general formula is:

LCOE = (Sum of all costs over lifetime) / (Sum of all energy produced over lifetime)

Both costs and energy produced are typically "levelized" or discounted back to their present value using the discount rate.

For this calculator, with only Capital Costs (CAPEX) as the cost input, and assuming uniform annual energy production and discounting, the formula becomes:

LCOE ($/kWh) ≈ CAPEX ($) / [Annual Energy Production (kWh) * Present Value Factor]

Where:

  • Annual Energy Production (kWh) = Plant Capacity (kW) * Capacity Factor (decimal) * 8760 (hours/year)
  • Present Value Factor = Sum from year=1 to Lifetime of (1 / (1 + Discount Rate (decimal))^year)
  • If Discount Rate is 0%, Present Value Factor = Lifetime (years)

Note: A full LCOE calculation would typically include Operating & Maintenance (O&M) costs, fuel costs, decommissioning costs, and potentially incentives or tax effects. This simplified tool provides a basic estimate based primarily on the initial investment and production potential.

LCOE Calculation Examples

These examples demonstrate how different inputs affect the LCOE. Note that real-world LCOE values are more complex.

Example 1: Small Rooftop Solar System

Scenario: Estimate LCOE for a residential solar PV system.

Inputs:

  • CAPEX: $15,000
  • Capacity: 5 kW
  • Capacity Factor: 18%
  • Lifetime: 25 years
  • Discount Rate: 6%

Calculation (Simplified):

  • Annual Energy ≈ 5 kW * 0.18 * 8760 hr/yr ≈ 7,884 kWh/yr
  • Present Value Factor (6%, 25 yrs) ≈ (1 - (1.06)^-25) / 0.06 ≈ 12.78
  • NPV of Energy ≈ 7,884 kWh/yr * 12.78 ≈ 100,700 kWh (PV equivalent)
  • LCOE ≈ $15,000 / 100,700 kWh ≈ $0.149 / kWh

Result: LCOE ≈ $0.149/kWh

Example 2: Utility-Scale Solar Farm

Scenario: Estimate LCOE for a large solar power plant.

Inputs:

  • CAPEX: $100,000,000
  • Capacity: 50 MW (50,000 kW)
  • Capacity Factor: 25%
  • Lifetime: 30 years
  • Discount Rate: 5%

Calculation (Simplified):

  • Annual Energy ≈ 50,000 kW * 0.25 * 8760 hr/yr ≈ 109,500,000 kWh/yr
  • Present Value Factor (5%, 30 yrs) ≈ (1 - (1.05)^-30) / 0.05 ≈ 15.37
  • NPV of Energy ≈ 109,500,000 kWh/yr * 15.37 ≈ 1,682,900,000 kWh (PV equivalent)
  • LCOE ≈ $100,000,000 / 1,682,900,000 kWh ≈ $0.059 / kWh

Result: LCOE ≈ $0.059/kWh

Example 3: Onshore Wind Farm

Scenario: Estimate LCOE for an onshore wind project.

Inputs:

  • CAPEX: $150,000,000
  • Capacity: 100 MW (100,000 kW)
  • Capacity Factor: 40%
  • Lifetime: 25 years
  • Discount Rate: 7%

Calculation (Simplified):

  • Annual Energy ≈ 100,000 kW * 0.40 * 8760 hr/yr ≈ 350,400,000 kWh/yr
  • Present Value Factor (7%, 25 yrs) ≈ (1 - (1.07)^-25) / 0.07 ≈ 11.65
  • NPV of Energy ≈ 350,400,000 kWh/yr * 11.65 ≈ 4,082,160,000 kWh (PV equivalent)
  • LCOE ≈ $150,000,000 / 4,082,160,000 kWh ≈ $0.037 / kWh

Result: LCOE ≈ $0.037/kWh

Example 4: Gas Peaker Plant (Low Capacity Factor)

Scenario: Estimate LCOE for a natural gas plant used only during peak demand.

Inputs:

  • CAPEX: $80,000,000
  • Capacity: 200 MW (200,000 kW)
  • Capacity Factor: 10%
  • Lifetime: 20 years
  • Discount Rate: 8%

Calculation (Simplified):

  • Annual Energy ≈ 200,000 kW * 0.10 * 8760 hr/yr ≈ 175,200,000 kWh/yr
  • Present Value Factor (8%, 20 yrs) ≈ (1 - (1.08)^-20) / 0.08 ≈ 9.818
  • NPV of Energy ≈ 175,200,000 kWh/yr * 9.818 ≈ 1,719,900,000 kWh (PV equivalent)
  • LCOE ≈ $80,000,000 / 1,719,900,000 kWh ≈ $0.047 / kWh

Result: LCOE ≈ $0.047/kWh

Note: Real gas plant LCOE is heavily influenced by fuel costs and O&M, not included in this basic model.

Example 5: Nuclear Power Plant (High CAPEX, High CF, Long Lifetime)

Scenario: Estimate LCOE for a nuclear plant.

Inputs:

  • CAPEX: $10,000,000,000
  • Capacity: 1,000 MW (1,000,000 kW)
  • Capacity Factor: 90%
  • Lifetime: 60 years
  • Discount Rate: 4%

Calculation (Simplified):

  • Annual Energy ≈ 1,000,000 kW * 0.90 * 8760 hr/yr ≈ 7,884,000,000 kWh/yr
  • Present Value Factor (4%, 60 yrs) ≈ (1 - (1.04)^-60) / 0.04 ≈ 23.79
  • NPV of Energy ≈ 7,884,000,000 kWh/yr * 23.79 ≈ 187,660,000,000 kWh (PV equivalent)
  • LCOE ≈ $10,000,000,000 / 187,660,000,000 kWh ≈ $0.053 / kWh

Result: LCOE ≈ $0.053/kWh

Note: Real nuclear LCOE is heavily influenced by complex O&M, fuel (relatively low), and decommissioning costs.

Example 6: Hydroelectric Dam (High CAPEX, Long Lifetime)

Scenario: Estimate LCOE for a large hydro plant.

Inputs:

  • CAPEX: $5,000,000,000
  • Capacity: 500 MW (500,000 kW)
  • Capacity Factor: 50%
  • Lifetime: 80 years
  • Discount Rate: 3%

Calculation (Simplified):

  • Annual Energy ≈ 500,000 kW * 0.50 * 8760 hr/yr ≈ 2,190,000,000 kWh/yr
  • Present Value Factor (3%, 80 yrs) ≈ (1 - (1.03)^-80) / 0.03 ≈ 28.77
  • NPV of Energy ≈ 2,190,000,000 kWh/yr * 28.77 ≈ 63,010,000,000 kWh (PV equivalent)
  • LCOE ≈ $5,000,000,000 / 63,010,000,000 kWh ≈ $0.079 / kWh

Result: LCOE ≈ $0.079/kWh

Example 7: High Discount Rate Impact

Scenario: Same as Example 1 (Small Solar) but with a higher discount rate.

Inputs:

  • CAPEX: $15,000
  • Capacity: 5 kW
  • Capacity Factor: 18%
  • Lifetime: 25 years
  • Discount Rate: 10%

Calculation (Simplified):

  • Annual Energy ≈ 7,884 kWh/yr (same as Ex 1)
  • Present Value Factor (10%, 25 yrs) ≈ (1 - (1.10)^-25) / 0.10 ≈ 9.077
  • NPV of Energy ≈ 7,884 kWh/yr * 9.077 ≈ 71,560 kWh (PV equivalent)
  • LCOE ≈ $15,000 / 71,560 kWh ≈ $0.209 / kWh

Result: LCOE ≈ $0.209/kWh

Conclusion: A higher discount rate significantly increases LCOE because future energy production is valued less today.

Example 8: Low Capacity Factor Impact

Scenario: Same as Example 2 (Utility Solar) but with a lower capacity factor.

Inputs:

  • CAPEX: $100,000,000
  • Capacity: 50 MW (50,000 kW)
  • Capacity Factor: 15%
  • Lifetime: 30 years
  • Discount Rate: 5%

Calculation (Simplified):

  • Annual Energy ≈ 50,000 kW * 0.15 * 8760 hr/yr ≈ 65,700,000 kWh/yr
  • Present Value Factor (5%, 30 yrs) ≈ 15.37 (same as Ex 2)
  • NPV of Energy ≈ 65,700,000 kWh/yr * 15.37 ≈ 1,009,600,000 kWh (PV equivalent)
  • LCOE ≈ $100,000,000 / 1,009,600,000 kWh ≈ $0.099 / kWh

Result: LCOE ≈ $0.099/kWh

Conclusion: A lower capacity factor dramatically increases LCOE because less energy is produced for the same upfront cost.

Example 9: Shorter Lifetime Impact

Scenario: Same as Example 3 (Onshore Wind) but with a shorter lifetime.

Inputs:

  • CAPEX: $150,000,000
  • Capacity: 100 MW (100,000 kW)
  • Capacity Factor: 40%
  • Lifetime: 15 years
  • Discount Rate: 7%

Calculation (Simplified):

  • Annual Energy ≈ 350,400,000 kWh/yr (same as Ex 3)
  • Present Value Factor (7%, 15 yrs) ≈ (1 - (1.07)^-15) / 0.07 ≈ 9.108
  • NPV of Energy ≈ 350,400,000 kWh/yr * 9.108 ≈ 3,191,500,000 kWh (PV equivalent)
  • LCOE ≈ $150,000,000 / 3,191,500,000 kWh ≈ $0.047 / kWh

Result: LCOE ≈ $0.047/kWh

Conclusion: A shorter lifetime means less total energy over which to spread the initial CAPEX, potentially increasing LCOE, although the discount rate effect is also reduced over a shorter period.

Example 10: Zero Discount Rate

Scenario: Calculate LCOE with no discounting (as if money has no time value).

Inputs:

  • CAPEX: $20,000
  • Capacity: 10 kW
  • Capacity Factor: 20%
  • Lifetime: 20 years
  • Discount Rate: 0%

Calculation (Simplified):

  • Annual Energy ≈ 10 kW * 0.20 * 8760 hr/yr ≈ 17,520 kWh/yr
  • Total Lifetime Energy ≈ 17,520 kWh/yr * 20 years = 350,400 kWh
  • LCOE ≈ $20,000 / 350,400 kWh ≈ $0.057 / kWh

Result: LCOE ≈ $0.057/kWh

Conclusion: When the discount rate is 0%, LCOE is simply Total CAPEX divided by Total Lifetime Energy Produced.

Frequently Asked Questions about LCOE

1. What does LCOE stand for?

LCOE stands for Levelized Cost of Energy.

2. What does LCOE measure?

LCOE measures the average cost in dollars per unit of energy (usually $/kWh or $/MWh) required to build and operate a power generation asset over its lifetime.

3. Why is LCOE useful?

LCOE is useful for comparing the cost-effectiveness of different power generation technologies (like solar, wind, gas, nuclear) that have different patterns of costs (e.g., high upfront CAPEX vs. high ongoing fuel costs).

4. What are the main factors included in a full LCOE calculation?

A full LCOE calculation typically includes Capital Costs (CAPEX), Operating and Maintenance (O&M) costs, Fuel Costs, Decommissioning Costs, and potentially incentives or tax effects, all discounted over the project lifetime.

5. What is the role of the Discount Rate in LCOE?

The discount rate accounts for the time value of money. It means that costs incurred and energy produced in the future are valued less than costs incurred and energy produced today. A higher discount rate places more weight on upfront costs (like CAPEX) compared to future costs or energy production.

6. How does Capacity Factor affect LCOE?

Capacity factor is crucial because it determines how much energy is actually produced. For a given set of costs, a higher capacity factor means more energy is produced over the lifetime, spreading the costs over a larger energy output and resulting in a lower LCOE.

7. Does this calculator include O&M or Fuel Costs?

No, this simplified calculator uses only Initial Investment Cost (CAPEX) as the cost input. A comprehensive LCOE would add discounted O&M, fuel, and decommissioning costs to the numerator.

8. What units should I use for inputs?

Input CAPEX in dollars ($), Capacity in kilowatts (kW), Capacity Factor and Discount Rate as percentages (%), and Lifetime in years. The output LCOE will be in dollars per kilowatt-hour ($/kWh).

9. What does a low LCOE mean?

A lower LCOE generally indicates a more cost-competitive source of electricity generation over its lifetime, assuming the LCOE calculation includes all relevant costs and uses an appropriate discount rate.

10. Can LCOE be used as the sole metric for comparing energy sources?

While very useful, LCOE has limitations. It doesn't typically account for integration costs (like transmission upgrades or the cost of backup power for intermittent sources), environmental externalities (like carbon emissions), or grid reliability needs (like dispatchability). It's best used as one metric among several for energy planning.

Ahmed mamadouh
Ahmed mamadouh

Engineer & Problem-Solver | I create simple, free tools to make everyday tasks easier. My experience in tech and working with global teams taught me one thing: technology should make life simpler, easier. Whether it’s converting units, crunching numbers, or solving daily problems—I design these tools to save you time and stress. No complicated terms, no clutter. Just clear, quick fixes so you can focus on what’s important.

We will be happy to hear your thoughts

Leave a reply

Cunits
Logo